Rock Slope Stabilization/ High Scaling

 

Resort Municipality of Whistler, Taluswood Drive, Whistler BC  2009

High scaling, danger tree removal, removal and replacement of damaged shotcrete, drilling and installation of new drilled plastic drains in rock face to improve the safety of the rock slope above a municipal roadway.



BC Hydro, Southern Communities Grid Connection Project, Lillooet Lake, BC  2010

High scaling and danger tree removal along forest service road in preparation for new power line construction to serve remote communities located along the Lillooet River in southwestern BC.



BC Ministry of Forests and Range, Chilliwack Lake, BC  2010

Trim blasting of an un-stable rock mass, high scaling and danger tree removal to stabilize the remaining rock face after a major rockslide closed the forest service road.